Water Resources plans many waterworks, wastewater improvements through 2025

BATAVIA, OH — The Clermont County Water Resources Department’s 5-year Capital Improvement Plan (2021-2025) calls for many improvements to water mains, water tanks and sewers.

The waterworks plan calls for 60 waterworks capital improvements valued at $32.9 million, including 26 water main replacement projects ($16.8 million), eight elevated water tank inspection, rehab and painting projects ($4.3 million), 10 water treatment plant and well field improvement projects ($3 million), seven new infrastructure/expansion projects ($3.7 million) and three petition/assessment projects ($1.2 million).

The wastewater plan calls for 56 wastewater capital improvements estimated at $63.9 million, including 15 sewer replacement/rehabilitation projects ($22.6 million), nine lift station replacement, upgrade or elimination projects ($10.4 million), 10 wastewater treatment plant improvement or elimination projects ($13.0 million), four new infrastructure/expansion projects ($3.3 million), and eight petition/assessment projects ($12.9 million).

Waterworks capital improvement funding includes:

Available funding (2021-2025) $45,686,096

Wastewater capital improvement funding includes:

Available funding (2021-2025) $62,369,811

Water main replacement projects include:

Elevated water tank inspection, rehab and painting projects include:

Sewer replacement/rehabilitation projects include:

Lift station replacement, upgrade or elimination projects include:

Wastewater Treatment Plant Improvements or Elimination projects include: