Public Hearing: Taylor Avenue Water Petition Project – in Stonelick Township

Clermont Sun:  Two consecutive weeks commencing on 08/16/2018

LEGAL NOTICE

On August 8, 2018, the Board of County Commissioners of the County of Clermont, Ohio, adopted Resolution Number 131-18 declaring the necessity to construct certain improvements for the County Waterworks System in the Clermont County Water Resources Department, Clermont County, Ohio.

The proposed improvements are described as follows:

This project consists of the installation of approximately 611 linear feet of 6” ductile iron water main and appurtenances along Taylor Avenue located in Stonelick Township, beginning at the intersection of Stonelick-Williams Corner Road and Taylor Avenue and extending northwestwardly along Taylor Avenue. The Project is identified as Project Number 6401-60149 known as the Taylor Avenue Water Petition Project.  The cost of the Project, including construction costs, engineering fees, legal and administrative fees, and all necessary and incidental expenses in connection therewith, is currently estimated at $105,576.00, and shall be paid from special assessment (cash payment or certification to the tax bill) of benefited property abutting on the water line extension or right-of-way in which it is constructed in the form of a Basic Benefit Assessment with the assessable project costs assessed per benefited parcel (total assessable project costs estimated at $70,000.00) and an Improvement Benefit Assessment at the option of the property owner for all improved or unimproved properties (estimated at $23,176.00) or General Obligation Bonds or Notes issued in anticipation thereof pursuant to Chapters 6103 and 133 of the Ohio Revised Code, and a contribution by the County Waterworks System Capital Improvement Fund (estimated at $12,400.00).

Pursuant to Chapter 6103 of the Ohio Revised Code, notice is hereby given that endorsements of and/or objections to the construction of said improvements, the location, and the estimates of cost and financing, and tentative assessments thereof, all described in said Resolution, will be heard by the Board of County Commissioners at 11:00 A.M. Local Time on Wednesday, September 26, 2018, in the Session Room of the Office of the Board of County Commissioners, 101 East Main Street, Batavia, Ohio 45103.  At such time and place, a public hearing will be granted by such Board of County Commissioners to all interested parties.

A copy of said Resolution, the plans, specifications, estimates of costs and financing, and tentative assessments for such improvements are on file in the Office of the Board of County Commissioners, 101 East Main Street, Batavia, Ohio 45103 and the Office of the Clermont County Water Resources Department, 4400 Haskell Lane, Batavia, Ohio 45103, where they may be examined.

Property owners to be assessed have the right to pay their assessment principal in cash during at least a thirty (30) day period following passage of the resolution levying final assessments, or property owners may pay their assessment over the assessment period, which shall not exceed twenty (20) years, at the calculated uniform interest rate necessary to pay assessment bond interest as sold.

Written objections to or endorsements of the proposed improvements, the character and termini thereof, the boundaries of the improvement area, or the estimates of cost and financing, and tentative assessments thereof shall be received by such Board of County Commissioners for a period of five (5) days after such hearing.

This notice is also posted on the contracting authority’s website at the following URL link: www.clermontcountyohio.gov. In order to view the legal notice click on the link “Legal Notices” located on the Clermont County Home Page under County Government.

Clermont County Board of Commissioners

Edwin H. Humphrey, President
David L. Painter, Vice President
David H. Uible, Member

ATTEST:

_______________________________

Judith Kocica, Clerk of the Board